nerdexam
PeopleCert

CMS7 · Question #264

Which process would you MOST expect to be involved in the management of Underpinning Contracts?

The correct answer is D. Supplier Manager. See the full explanation below for the reasoning.

Question

Which process would you MOST expect to be involved in the management of Underpinning Contracts?

Options

  • AIT Designer/Architect
  • BProcess Manager
  • CService Catalogue Manager
  • DSupplier Manager

How the community answered

(47 responses)
  • A
    6% (3)
  • B
    17% (8)
  • C
    4% (2)
  • D
    72% (34)

Community Discussion

No community discussion yet for this question.

Full CMS7 Practice