nerdexam
PeopleCert

CMS7 · Question #205

Which one of the following includes four stages called Plan, Do, Check and Act?

The correct answer is A. The Deming Cycle. See the full explanation below for the reasoning.

Question

Which one of the following includes four stages called Plan, Do, Check and Act?

Options

  • AThe Deming Cycle
  • BThe continual service improvement approach
  • CThe seven-step improvement process
  • DThe service lifecycle

How the community answered

(23 responses)
  • A
    74% (17)
  • B
    4% (1)
  • C
    9% (2)
  • D
    13% (3)

Community Discussion

No community discussion yet for this question.

Full CMS7 Practice