The remediation plan should be evaluated at what point in the change lifecycle?

The correct answer is A. Before the change is approved. See the full explanation below for the reasoning.

Question

The remediation plan should be evaluated at what point in the change lifecycle?

Options

  • ABefore the change is approved
  • BImmediately after the change has failed and needs to be backed out
  • CAfter implementation but before the post implementation review
  • DAfter the post implementation review has identified a problem with the change

How the community answered

(42 responses)
  • A
    74% (31)
  • B
    7% (3)
  • C
    2% (1)
  • D
    17% (7)