nerdexam
ASQ

CMQ-OE · Question #35

Given a four-week project involving 22 tasks, a budget of $22,000, and a part-time team (project manager and two analysts), which project management tool will most likely be used to display project…

The correct answer is D. Gantt/milestone chart. See the full explanation below for the reasoning.

Question

Given a four-week project involving 22 tasks, a budget of $22,000, and a part-time team (project manager and two analysts), which project management tool will most likely be used to display project progress to management?

Options

  • AWork breakdown structure
  • BNetwork diagram
  • CBudget variance report
  • DGantt/milestone chart

How the community answered

(44 responses)
  • A
    5% (2)
  • B
    16% (7)
  • C
    7% (3)
  • D
    73% (32)

Community Discussion

No community discussion yet for this question.

Full CMQ-OE Practice