ASQ
CMQ-OE · Question #35
CMQ-OE Question #35: Real Exam Question with Answer & Explanation
The correct answer is D. Gantt/milestone chart. See the full explanation below for the reasoning.
Question
Given a four-week project involving 22 tasks, a budget of $22,000, and a part-time team (project manager and two analysts), which project management tool will most likely be used to display project progress to management?
Options
- AWork breakdown structure
- BNetwork diagram
- CBudget variance report
- DGantt/milestone chart
Community Discussion
No community discussion yet for this question.