Given a four-week project involving 22 tasks, a budget of $22,000, and a part-time team (project manager and two analysts), which project management tool will most likely be used to display project progress to management?

Options

  • AWork breakdown structure
  • BNetwork diagram
  • CBudget variance report
  • DGantt/milestone chart