CMQ-OE · Question #31
Which of the following is the biggest problem in cost璪enefit analysis?
The correct answer is B. It is easier to accurately estimate costs than benefits. See the full explanation below for the reasoning.
Question
Which of the following is the biggest problem in cost璪enefit analysis?
Options
- AIt is easier to accurately estimate benefits than costs.
- BIt is easier to accurately estimate costs than benefits.
- CIt is an elaborate tool requiring extensive computer support.
- DIt is too difficult to compute the time value of money.
How the community answered
(49 responses)- A8% (4)
- B73% (36)
- C14% (7)
- D4% (2)