GAQM
CLSSYB · Question #97
A Belt gathered the following defect data for a polyurethane production line and wanted to assemble it into a Pareto Chart. The correct order from left to right in the chart would be…
The correct answer is C. Recording the measurement. The length of wooden beams being sawed is measured by a line operator. Which is least likely to be influenced by the instrument?
Measure Phase Basics
Question
A Belt gathered the following defect data for a polyurethane production line and wanted to assemble it into a Pareto Chart. The correct order from left to right in the chart would be:
Data:Trimming37 Forming61 Packaging29 Sealing5
Options
- ACalibration of the instrument
- BActual temperature of the liquid
- CRecording the measurement
- DReading of the instrument
How the community answered
(49 responses)- A10% (5)
- B2% (1)
- C82% (40)
- D6% (3)
Explanation
The length of wooden beams being sawed is measured by a line operator. Which is least likely to be influenced by the instrument?
Topics
#Pareto Chart#defect data#data ordering#quality tools