When a Belt wishes to clarify the activities of various departments in a Process Map she is creating she adds a feature to the map called ______________.

The correct answer is C. Swim Lanes. You've hit your limit · resets 12:50am (America/New_York)

Measure Phase Basics

Question

When a Belt wishes to clarify the activities of various departments in a Process Map she is creating she adds a feature to the map called ______________.

Options

  • ADepartment Dividers
  • BPassing Lanes
  • CSwim Lanes
  • DResponsibility Paths

How the community answered

(20 responses)
  • C
    95% (19)
  • D
    5% (1)