When a Belt wishes to clarify the activities of various departments in a Process Map she is creating she adds a feature to the map called ______________.
The correct answer is C. Swim Lanes. You've hit your limit · resets 12:50am (America/New_York)
Measure Phase Basics
Question
When a Belt wishes to clarify the activities of various departments in a Process Map she is creating she adds a feature to the map called ______________.
Options
- ADepartment Dividers
- BPassing Lanes
- CSwim Lanes
- DResponsibility Paths
How the community answered
(20 responses)- C95% (19)
- D5% (1)
Explanation