The RPN or Risk Priority Number is used to rank the various Failure Modes as to their impact on the output of the subject process.

The correct answer is A. True. You've hit your limit · resets 12:50am (America/New_York)

Analyze Phase Basics

Question

The RPN or Risk Priority Number is used to rank the various Failure Modes as to their impact on the output of the subject process.

Options

  • ATrue
  • BFalse

How the community answered

(20 responses)
  • A
    95% (19)
  • B
    5% (1)

Explanation

You've hit your limit · resets 12:50am (America/New_York)

Topics

#FMEA#RPN#Risk Priority Number#failure mode ranking