CLSSYB · Question #28

When we create a Process Map we use a __________ to show the direction of work flow.

The correct answer is A. Solid line arrow. You've hit your limit · resets 12:50am (America/New_York)

Measure Phase Basics

Question

When we create a Process Map we use a __________ to show the direction of work flow.

Options

  • ASolid line arrow
  • BDashed line arrow
  • CSeries of dots
  • DDouble lines

How the community answered

(54 responses)
  • A
    87% (47)
  • B
    2% (1)
  • C
    4% (2)
  • D
    7% (4)

Explanation

You've hit your limit · resets 12:50am (America/New_York)

Topics

#Process Map#workflow direction#process symbols#flowchart notation

Community Discussion

No community discussion yet for this question.