Which element of waste best describes "the cost of an idle resource"?
The correct answer is A. Waiting. You've hit your limit · resets 12:50am (America/New_York)
Lean Six Sigma Overview and Principles
Question
Which element of waste best describes "the cost of an idle resource"?
Options
- AWaiting
- BMotion
- CInventory
- DCorrection
How the community answered
(25 responses)- A92% (23)
- B4% (1)
- C4% (1)