If a process has Outliers which pair of charts is most preferable if subgroups will exist for the Continuous Data?

The correct answer is B. Xbar-R Charts. You've hit your limit · resets 12:50am (America/New_York)

Control Phase

Question

If a process has Outliers which pair of charts is most preferable if subgroups will exist for the Continuous Data?

Options

  • AIndividual--Moving Range
  • BXbar-R Charts
  • CXbar-S Charts
  • DnP and P Charts

How the community answered

(39 responses)
  • A
    3% (1)
  • B
    74% (29)
  • C
    15% (6)
  • D
    8% (3)

Explanation

You've hit your limit · resets 12:50am (America/New_York)

Topics

#Xbar-R chart#SPC chart selection#continuous data#subgroups