CLSSBB · Question #48

A Belt working in a supply chain environment has to make a decision to change suppliers of critical raw materials for a new product upgrade. The purchasing manager is depending on the Belt's effort re

The correct answer is C. Only if the average cost per product upgrade is $4,060, will the purchase manager introduce new product upgrades with new components.. You've hit your limit · resets 12:50am (America/New_York)

Analyze Phase

Question

A Belt working in a supply chain environment has to make a decision to change suppliers of critical raw materials for a new product upgrade. The purchasing manager is depending on the Belt's effort requiring that the average cost of an internal critical raw material component be less than or equal to $4,200 in order to stay within budget. Using a sample of 35 first article components, a Mean of the new product upgrade price of $4,060, and a Standard Deviation of $98 was estimated. Select the answer that best states the Practical Problem.

Options

  • AIf the average cost per component is $4,200 or less, then the purchase manager will introduce the new product upgrade with new components.
  • BIf the average cost per component is greater than $4,200, then the purchase manager will introduce the new product upgrade with new components.
  • COnly if the average cost per product upgrade is $4,060, will the purchase manager introduce new product upgrades with new components.
  • DIf the average cost per new product upgrade is less than $180, then the purchase manager will introduce the new product upgrade with new components.

How the community answered

(28 responses)
  • A
    7% (2)
  • B
    4% (1)
  • C
    75% (21)
  • D
    14% (4)

Explanation

You've hit your limit · resets 12:50am (America/New_York)

Topics

#practical problem statement#hypothesis testing#one-sample t-test#supply chain

Community Discussion

No community discussion yet for this question.

Full CLSSBB Practice