CLOUD-DIGITAL-LEADER · Question #269
Your organization needs a large amount of extra computing power within the next two weeks. After those two weeks, the need for the additional resources will end. Which is the most cost-effective appro
The correct answer is C. Start a very powerful virtual machine without using a committed use discount. For short-term, temporary compute needs, on-demand virtual machines (pay-as-you-go) are the most cost-effective option. You only pay for the two weeks of actual use and then stop. A committed use discount (A) requires a 1- or 3-year commitment-paying for resources long after the
Question
Your organization needs a large amount of extra computing power within the next two weeks. After those two weeks, the need for the additional resources will end. Which is the most cost-effective approach?
Options
- AUse a committed use discount to reserve a very powerful virtual machine
- BPurchase one very powerful physical computer
- CStart a very powerful virtual machine without using a committed use discount
- DPurchase multiple physical computers and scale workload across them
How the community answered
(58 responses)- A3% (2)
- B7% (4)
- C88% (51)
- D2% (1)
Explanation
For short-term, temporary compute needs, on-demand virtual machines (pay-as-you-go) are the most cost-effective option. You only pay for the two weeks of actual use and then stop. A committed use discount (A) requires a 1- or 3-year commitment-paying for resources long after the need ends, making it far more expensive for a two-week scenario. Purchasing physical computers (B and D) involves large upfront capital costs and the hardware remains underutilized after the two-week period, making them the least cost-effective options.
Topics
Community Discussion
No community discussion yet for this question.