Which of the following are essential steps to take when creating a virtual server?

The correct answer is C. Select a machine image to run, select security credentials, select the size of the virtual. See the full explanation below for the reasoning.

Question

Which of the following are essential steps to take when creating a virtual server?

Options

  • ASelect a machine image to run, select an application set to run, select security credentials.
  • BSelect a machine image to run, select an application set to run, select the size of the virtual
  • CSelect a machine image to run, select security credentials, select the size of the virtual
  • DSelect an application set to run, select security credentials, select the size of the virtual

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    81% (22)
  • D
    11% (3)