An existing capability is being migrated into the cloud. Capacity management issues have been noticed in the past and an exercise is being performed to calculate current and future volumes. In which…

The correct answer is B. Design. See the full explanation below for the reasoning.

Question

An existing capability is being migrated into the cloud. Capacity management issues have been noticed in the past and an exercise is being performed to calculate current and future volumes. In which of the following lifecycle phases is this likely to be performed?

Options

  • AOperation
  • BDesign
  • CTransition
  • DStrategy

How the community answered

(20 responses)
  • A
    10% (2)
  • B
    85% (17)
  • C
    5% (1)

Community Discussion

No community discussion yet for this question.

Full CLO-001 Practice