CISSP · Question #890
The security accreditation task of the System Development Life Cycle (SDLC) process is completed at the end of which phase?
The correct answer is D. System implementation. In the System Development Life Cycle (SDLC), security accreditation typically occurs at the end of the System Implementation phase. This phase involves the final steps of building, configuring, and deploying the system, and it is where the system undergoes rigorous testing…
Question
The security accreditation task of the System Development Life Cycle (SDLC) process is completed at the end of which phase?
Options
- ASystem acquisition and development
- BSystem operations and maintenance
- CSystem initiation
- DSystem implementation
How the community answered
(30 responses)- B7% (2)
- C3% (1)
- D90% (27)
Explanation
In the System Development Life Cycle (SDLC), security accreditation typically occurs at the end of the System Implementation phase. This phase involves the final steps of building, configuring, and deploying the system, and it is where the system undergoes rigorous testing, validation, and security reviews. The security accreditation process ensures that the system meets all security requirements and that risks are properly mitigated before the system goes live.