According to the Capability Maturity Model Integration (CMMI), which of the following levels is identified by a managed process that is tailored from the organization's set of standard processes accor
The correct answer is D. Level 3: Defined. In CMMI, Level 3 (Defined) is characterized by processes that are tailored from the organization's standard process set using established tailoring guidelines, making them consistent and organization-wide.
Question
According to the Capability Maturity Model Integration (CMMI), which of the following levels is identified by a managed process that is tailored from the organization's set of standard processes according to the organization's tailoring guidelines?
Options
- ALevel 0: Incomplete
- BLevel 1: Performed
- CLevel 2: Managed
- DLevel 3: Defined
How the community answered
(24 responses)- A4% (1)
- D96% (23)
Why each option
In CMMI, Level 3 (Defined) is characterized by processes that are tailored from the organization's standard process set using established tailoring guidelines, making them consistent and organization-wide.
Level 0 (Incomplete) describes a process that is either not performed or only partially performed, with no defined outcomes or managed attributes.
Level 1 (Performed) describes a process that accomplishes the needed work to produce work products but lacks the rigor of planning, monitoring, or organizational standards.
Level 2 (Managed) describes a process that is planned, monitored, and controlled at the project level, but it is not yet tailored from an organizational set of standard processes, which is the hallmark of Level 3.
At CMMI Maturity Level 3 (Defined), processes are well-characterized, understood, and described in standards, procedures, tools, and methods. The key distinguishing feature is that processes are proactively tailored from the organization's set of standard processes according to tailoring guidelines, ensuring consistency across projects while allowing controlled customization. This differs from Level 2 where processes are managed reactively at the project level without reference to an organizational standard.
Concept tested: CMMI maturity levels and defined process characteristics