CISSP · Question #407
What should be used immediately after a Business Continuity Plan (BCP) has been invoked?
The correct answer is B. Emergency procedures describing the necessary actions to be taken following an incident. Emergency procedures are the first step in the business continuity process, as they aim to protect the safety of people and assets, and to minimize the impact of the incident. Emergency procedures should be used immediately after a BCP has been invoked, as they provide guidance o
Question
What should be used immediately after a Business Continuity Plan (BCP) has been invoked?
Options
- AResumption procedures describing the actions to be taken to return to normal business
- BEmergency procedures describing the necessary actions to be taken following an incident
- CFallback procedures describing what action are to be taken to more essential business activities
- DMaintain schedule how and the plan will be tested and the process for maintaining the plan
How the community answered
(33 responses)- A3% (1)
- B91% (30)
- C6% (2)
Explanation
Emergency procedures are the first step in the business continuity process, as they aim to protect the safety of people and assets, and to minimize the impact of the incident. Emergency procedures should be used immediately after a BCP has been invoked, as they provide guidance on how to respond to the crisis and restore critical functions as soon as possible.