CISSP · Question #1233
CISSP Question #1233: Real Exam Question with Answer & Explanation
The correct answer is B: User Acceptance Testing (UAT) before implementation. User Acceptance Testing (UAT) before implementation is one of the steps included in change management. Change management is a process that ensures that any changes to the system or the environment are planned, approved, tested, implemented, and documented in a controlled and cons
Question
Which of the following is included in change management?
Options
- ABusiness continuity testing
- BUser Acceptance Testing (UAT) before implementation
- CTechnical review by business owner
- DCost-benefit analysis (CBA) after implementation
Explanation
User Acceptance Testing (UAT) before implementation is one of the steps included in change management. Change management is a process that ensures that any changes to the system or the environment are planned, approved, tested, implemented, and documented in a controlled and consistent manner. UAT is a type of testing that involves the end users or the stakeholders of the system, and it verifies that the system meets the functional and non-functional requirements and expectations. UAT is usually performed before the implementation of the system or the change, as a final validation step.
Topics
Community Discussion
No community discussion yet for this question.