Which of the following is included in change management?
The correct answer is B. User Acceptance Testing (UAT) before implementation. User Acceptance Testing (UAT) before implementation is one of the steps included in change management. Change management is a process that ensures that any changes to the system or the environment are planned, approved, tested, implemented, and documented in a controlled and cons
Question
Which of the following is included in change management?
Options
- ABusiness continuity testing
- BUser Acceptance Testing (UAT) before implementation
- CTechnical review by business owner
- DCost-benefit analysis (CBA) after implementation
How the community answered
(36 responses)- A8% (3)
- B86% (31)
- C3% (1)
- D3% (1)
Explanation
User Acceptance Testing (UAT) before implementation is one of the steps included in change management. Change management is a process that ensures that any changes to the system or the environment are planned, approved, tested, implemented, and documented in a controlled and consistent manner. UAT is a type of testing that involves the end users or the stakeholders of the system, and it verifies that the system meets the functional and non-functional requirements and expectations. UAT is usually performed before the implementation of the system or the change, as a final validation step.