The correct answer is C: Program sponsor. The change management role that is responsible for the overall success of the project and supporting the change throughout the organization is the program sponsor. The program sponsor is the senior executive or stakeholder who provides the vision, direction, and support for the c

Submitted by ngozi_ng· Mar 5, 2026Security and Risk Management

Question

Which change management role is responsible for the overall success of the project and supporting the change throughout the organization?

Options

  • AChange driver
  • BChange implementer
  • CProgram sponsor
  • DProject manager

Explanation

The change management role that is responsible for the overall success of the project and supporting the change throughout the organization is the program sponsor. The program sponsor is the senior executive or stakeholder who provides the vision, direction, and support for the change management project, and who ensures the alignment and integration of the change management project with the business goals and strategy of the organization. The program sponsor is responsible for the overall success of the project and supporting the change throughout the organization, as they can provide the leadership, guidance, and resources for the change management project, and communicate and advocate the benefits and value of the change management project to the other stakeholders, such as the management, the employees, or the customers.

Topics

#change management#program sponsor#organizational roles