The correct answer is D: Contingency plan. A contingency plan is a plan devised for a specific situation when things could go wrong. Contingency plans include specific strategies and actions to deal with specific variances to assumptions resulting in a particular problem, emergency, or state of affairs. They also include
Question
Which of the following recovery plans includes specific strategies and actions to deal with specific variances to assumptions resulting in a particular security problem, emergency, or state of affairs?
Options
- ABusiness continuity plan
- BDisaster recovery plan
- CContinuity of Operations Plan
- DContingency plan
Explanation
A contingency plan is a plan devised for a specific situation when things could go wrong. Contingency plans include specific strategies and actions to deal with specific variances to assumptions resulting in a particular problem, emergency, or state of affairs. They also include a monitoring process and triggers for initiating planned actions. Answer option B is incorrect. Disaster recovery is the process, policies, and procedures related to preparing for recovery or continuation of technology infrastructure critical to an organization after a natural or human-induced disaster. Answer option A is incorrect. It deals with the plans and procedures that identify and prioritize the critical business functions that must be preserved. Answer option C is incorrect. It includes the plans and procedures documented that ensure the continuity of critical operations during any period where normal operations are impossible.