CISSP-ISSEP · Question #83

CISSP-ISSEP Question #83: Real Exam Question with Answer & Explanation

The correct answer is A: development baseline. A development baseline is an approved build of the product that serves as a fixed reference point - it can represent a single component or a combination of components that have been formally accepted at a specific stage in development. Option A is correct because the definition o

Systems Development and Acquisition

Question

Fill in the blanks with an appropriate phrase. A ________ is an approved build of the product, and can be a single component or a combination of components.

Options

  • Adevelopment baseline

Explanation

A development baseline is an approved build of the product that serves as a fixed reference point - it can represent a single component or a combination of components that have been formally accepted at a specific stage in development.

Option A is correct because the definition of a development baseline precisely matches the blank: it is an approved, controlled version of the product (or part of it) used as a foundation for further development and change management.

There are no other distractors listed in this question, so comparison isn't applicable here - the single choice maps directly to the definition.

Memory tip: Think of "baseline" like a base camp on a mountain - it's the approved, stable point you return to and build from. "Development" tells you it's tied to the product build lifecycle, not documentation or testing.

Topics

#Configuration Management#Development Baselines#System Development Life Cycle#Software Engineering

Community Discussion

No community discussion yet for this question.

Full CISSP-ISSEP PracticeBrowse All CISSP-ISSEP Questions