CISSP-ISSEP · Question #53
Which of the following tasks prepares the technical management plan in planning the technical effort?
The correct answer is B. Task 9. Task 9 is correct because it is specifically designated as the task responsible for preparing the Technical Management Plan (TMP) - the foundational document that governs how the technical effort will be organized, executed, and controlled throughout a project. In most systems en
Question
Which of the following tasks prepares the technical management plan in planning the technical effort?
Options
- ATask 10
- BTask 9
- CTask 7
- DTask 8
How the community answered
(25 responses)- B92% (23)
- C4% (1)
- D4% (1)
Explanation
Task 9 is correct because it is specifically designated as the task responsible for preparing the Technical Management Plan (TMP) - the foundational document that governs how the technical effort will be organized, executed, and controlled throughout a project. In most systems engineering frameworks (such as INCOSE), tasks within the Technical Planning process are assigned distinct, sequential responsibilities, and Task 9 is the one explicitly mapped to TMP preparation.
Why the distractors are wrong:
- Task 7 (C) typically addresses defining the technical effort scope or establishing the technical approach, not writing the plan itself.
- Task 8 (D) generally focuses on identifying technical risks or constraints that feed into the plan rather than authoring it.
- Task 10 (A) usually comes after plan preparation - commonly involving review, approval, or baseline establishment of the plan.
Memory tip: Think of the tasks as a pipeline - scope → inputs → WRITE THE PLAN (Task 9) → approve. Task 9 sits at the center of that pipeline because you can't write the plan until you've gathered inputs (Task 8) and can't approve it until it's written. Nine = "nailing it down" on paper.