CISSP-ISSEP · Question #134
Which of the following sections of the SEMP template defines the project constraints, to include constraints on funding, personnel, facilities, manufacturing capability and capacity, critical resource
The correct answer is B. Section 3.1.8. Section 3.1.8 of the SEMP template is specifically designated as the "Constraints" section, where teams document limitations that will shape the systems engineering effort - covering funding caps, available personnel, facility limitations, manufacturing capability/capacity, criti
Question
Which of the following sections of the SEMP template defines the project constraints, to include constraints on funding, personnel, facilities, manufacturing capability and capacity, critical resources, and other constraints?
Options
- ASection 3.1.5
- BSection 3.1.8
- CSection 3.1.9
- DSection 3.1.7
How the community answered
(21 responses)- A5% (1)
- B90% (19)
- D5% (1)
Explanation
Section 3.1.8 of the SEMP template is specifically designated as the "Constraints" section, where teams document limitations that will shape the systems engineering effort - covering funding caps, available personnel, facility limitations, manufacturing capability/capacity, critical resources, and any other binding restrictions on the program.
Why the distractors are wrong:
- Section 3.1.5 typically covers the System Status or technical baseline description, not constraints.
- Section 3.1.7 generally addresses Applicable Documents or related program agreements, not resource/funding constraints.
- Section 3.1.9 typically covers Program/Project Risks or risk management inputs - related to constraints but a distinct section focused on uncertainty rather than hard limits.
Memory tip: Think of 3.1.8 as "8arriers" - the barriers (constraints) that bound what the project can do. Constraints come before risks (3.1.9) in the template because you must know your hard limits before you can assess what's uncertain.