CISM · Question #958
CISM Question #958: Real Exam Question with Answer & Explanation
The correct answer is D: Parallel test. Parallel testing activates the actual disaster recovery systems and runs them concurrently alongside live production systems, producing real, measurable results without ever taking production offline - making it the best balance of accuracy and minimal disruption. Why the distrac
Question
An organization wants to test its disaster recovery plan (DRP) for a mission-critical system while minimizing production downtime. Which of the following will provide the MOST accurate test results for the plan while meeting the organizational goals?
Options
- AStructured walk-through
- BSimulation test
- CChecklist review
- DParallel test
Explanation
Parallel testing activates the actual disaster recovery systems and runs them concurrently alongside live production systems, producing real, measurable results without ever taking production offline - making it the best balance of accuracy and minimal disruption.
Why the distractors fail:
- A (Structured walk-through): Teams verbally discuss what they would do step-by-step, but no systems are actually invoked - results are theoretical, not empirical.
- B (Simulation test): A realistic scenario is enacted, but it typically stops short of full system failover, so you're testing human response more than the technical recovery process itself.
- C (Checklist review): The least rigorous option - it only confirms the plan exists and appears complete, with zero live system involvement.
Memory tip: Picture the options on a spectrum from "paperwork" to "pulling the plug" - Checklist → Walk-through → Simulation → Parallel → Full Interruption. The question asks you to stop just before full interruption: parallel testing is the last step before you'd actually risk production, which is exactly why it's the most accurate without causing downtime.