CISM · Question #931
Which of the following should be considered FIRST when updating an organization's business continuity plan (BCP) after the acquisition of a new business?
The correct answer is B. Risk associated with the new business. After an acquisition, the first consideration for updating the BCP is assessing the risk associated with the new business (critical processes, dependencies, threats, and impacts). This determines continuity priorities and requirements before budgets or infrastructure plans are…
Question
Which of the following should be considered FIRST when updating an organization's business continuity plan (BCP) after the acquisition of a new business?
Options
- ABusiness strategy
- BRisk associated with the new business
- CUpdated IT budget
- DNew business infrastructure requirements
How the community answered
(41 responses)- A7% (3)
- B71% (29)
- C5% (2)
- D17% (7)
Explanation
After an acquisition, the first consideration for updating the BCP is assessing the risk associated with the new business (critical processes, dependencies, threats, and impacts). This determines continuity priorities and requirements before budgets or infrastructure plans are addressed.