CISM · Question #849
Which of the following is MOST important to consider when deciding whether to accept residual risk?
The correct answer is B. Cost of additional mitigation. Residual risk is the risk remaining after controls have already been applied. The decision to accept it is fundamentally a cost-benefit analysis: if the cost of further mitigation (B) exceeds the potential loss or impact of the risk, acceptance is the rational business decision.
Question
Which of the following is MOST important to consider when deciding whether to accept residual risk?
Options
- AClassification of the information
- BCost of additional mitigation
- CAnnual rate of occurrence
- DCost of replacing the asset
How the community answered
(29 responses)- A3% (1)
- B83% (24)
- C10% (3)
- D3% (1)
Explanation
Residual risk is the risk remaining after controls have already been applied. The decision to accept it is fundamentally a cost-benefit analysis: if the cost of further mitigation (B) exceeds the potential loss or impact of the risk, acceptance is the rational business decision. This is the core of risk treatment decision-making. Information classification (A) helps prioritize risks but does not directly drive the accept/treat decision. Annual rate of occurrence (C) is an input to calculating risk exposure but must be weighed against mitigation cost. Asset replacement cost (D) informs impact severity but alone does not determine whether to invest in additional controls. The cost of mitigation relative to the residual risk exposure is the deciding factor.
Topics