Isaca
CISM · Question #831
Which of the following BEST prepares an organization for disaster recovery?
The correct answer is C. Business continuity plan (BCP). A business continuity plan (BCP) best prepares an organization for disaster recovery by defining how critical business functions will continue during and after a disruption, including recovery priorities and coordination needed to support disaster recovery activities.
Submitted by kevin_r· Apr 18, 2026Information Security Program Development and Management
Question
Which of the following BEST prepares an organization for disaster recovery?
Options
- AFailover testing
- BAn incident response policy
- CBusiness continuity plan (BCP)
- DSecurity awareness training
How the community answered
(21 responses)- B5% (1)
- C90% (19)
- D5% (1)
Explanation
A business continuity plan (BCP) best prepares an organization for disaster recovery by defining how critical business functions will continue during and after a disruption, including recovery priorities and coordination needed to support disaster recovery activities.
Topics
#Business Continuity#Disaster Recovery#Business Continuity Plan (BCP)#Organizational Resilience