nerdexam
Isaca

CISM · Question #815

The manager of a key project has bypassed the standard contractor onboarding process to acquire additional resources for delivering the project on time. Contracts were executed offline, and contractor

The correct answer is D. There are insufficient contractual requirements in place to govern third-party arrangements.. The PRIMARY concern is that no formal contracts with proper security, compliance, and governance clauses were established. Standard contractor onboarding exists specifically to ensure legal agreements capture requirements around data handling, confidentiality, liability, access c

Submitted by yaw92· Apr 18, 2026Information Security Governance

Question

The manager of a key project has bypassed the standard contractor onboarding process to acquire additional resources for delivering the project on time. Contracts were executed offline, and contractors were provided organizational access without going through the standard due diligence process. Which of the following should be the PRIMARY concern?

Options

  • AThe project may be delayed further if the incident is reported.
  • BThe contractors may inappropriately outsource the business functions to fourth-party suppliers.
  • CThe contractors may not operate in line with industry benchmarks.
  • DThere are insufficient contractual requirements in place to govern third-party arrangements.

How the community answered

(38 responses)
  • A
    16% (6)
  • B
    3% (1)
  • C
    8% (3)
  • D
    74% (28)

Explanation

The PRIMARY concern is that no formal contracts with proper security, compliance, and governance clauses were established. Standard contractor onboarding exists specifically to ensure legal agreements capture requirements around data handling, confidentiality, liability, access controls, and termination rights. Without these contractual protections, the organization has no enforceable mechanism to govern the third parties' behavior. Delay risk (A) is a secondary operational concern, not a security governance concern. Fourth-party outsourcing (B) and industry benchmarks (C) are subordinate risks that stem from the absence of proper contractual requirements - making D the root cause.

Topics

#Third-party risk management#Contractual security#Due diligence#Governance oversight

Community Discussion

No community discussion yet for this question.

Full CISM Practice