CISM · Question #802
Which of the following would be the BEST way to reduce the risk of disruption resulting from an emergency system change?
The correct answer is C. Confirm rollback plans are in place.. The best way to reduce the risk of disruption from an emergency system change is to confirm rollback plans are in place. According to the CISM Review Manual, having an effective rollback (or backout) plan ensures that if the emergency change causes unexpected issues, the organiza
Question
Which of the following would be the BEST way to reduce the risk of disruption resulting from an emergency system change?
Options
- AConfirm the change implementation is scheduled.
- BVerify the change request has been approved.
- CConfirm rollback plans are in place.
- DNotify users affected by the change.
How the community answered
(17 responses)- A29% (5)
- B18% (3)
- C41% (7)
- D12% (2)
Explanation
The best way to reduce the risk of disruption from an emergency system change is to confirm rollback plans are in place. According to the CISM Review Manual, having an effective rollback (or backout) plan ensures that if the emergency change causes unexpected issues, the organization can quickly revert to a known, stable state. This minimizes downtime and impact to business operations. Approval and communication are important, but only a rollback plan directly addresses risk reduction during unexpected disruptions.