An organization requires that business-critical applications be recovered within 30 minutes in the event of a disaster. Which of the following metrics should be in the business continuity plan (BCP)…
The correct answer is D. Recovery time objective (RTO). The Recovery Time Objective (RTO) defines the maximum acceptable downtime for a business function or system following a disruption. If the organization requires recovery in 30 minutes, that is the system's RTO. This metric guides the selection of technologies, staffing, and…
Question
An organization requires that business-critical applications be recovered within 30 minutes in the event of a disaster. Which of the following metrics should be in the business continuity plan (BCP) to manage this requirement?
Options
- AMaximum tolerable downtime (MTD)
- BService level agreement (SLA)
- CRecovery point objective (RPO)
- DRecovery time objective (RTO)
How the community answered
(31 responses)- A10% (3)
- B3% (1)
- D87% (27)
Explanation
The Recovery Time Objective (RTO) defines the maximum acceptable downtime for a business function or system following a disruption. If the organization requires recovery in 30 minutes, that is the system's RTO. This metric guides the selection of technologies, staffing, and procedures needed to meet recovery expectations. "RTO defines the target time set for the recovery of IT and business activities after a disruption. It is a key BCP design parameter."