CISM · Question #779
A business continuity plan (BCP) should contain:
The correct answer is D. Criteria for activation. Criteria for activation are essential to ensure that the BCP is triggered appropriately in response to a disruption. "The BCP should include clearly defined activation criteria to ensure that plans are invoked when
Submitted by yousef_jo· Apr 18, 2026Information Security Program Development and Management
Question
A business continuity plan (BCP) should contain:
Options
- AHardware and software inventories
- BData restoration procedures
- CInformation about eradication activities
- DCriteria for activation
How the community answered
(47 responses)- A6% (3)
- B2% (1)
- C2% (1)
- D89% (42)
Explanation
Criteria for activation are essential to ensure that the BCP is triggered appropriately in response to a disruption. "The BCP should include clearly defined activation criteria to ensure that plans are invoked when
Topics
#Business Continuity Planning#BCP Activation#Resilience Planning