A business continuity plan (BCP) should contain:

The correct answer is D. Criteria for activation. Criteria for activation are essential to ensure that the BCP is triggered appropriately in response to a disruption. "The BCP should include clearly defined activation criteria to ensure that plans are invoked when

Submitted by yousef_jo· Apr 18, 2026Information Security Program Development and Management

Question

A business continuity plan (BCP) should contain:

Options

  • AHardware and software inventories
  • BData restoration procedures
  • CInformation about eradication activities
  • DCriteria for activation

How the community answered

(47 responses)
  • A
    6% (3)
  • B
    2% (1)
  • C
    2% (1)
  • D
    89% (42)

Explanation

Criteria for activation are essential to ensure that the BCP is triggered appropriately in response to a disruption. "The BCP should include clearly defined activation criteria to ensure that plans are invoked when