Question

An organization requires that business critical applications be recovered within 30 minutes in the event of a disaster. Which of the following metrics should be defined in the business continuity plan (BCP) to manage this requirement?

Options

  • AMaximum tolerable downtime (MTD)
  • BService level agreement (SLA)
  • CRecovery point objective (RPO)
  • DRecovery time objective (RTO)

Unlock CISM to see the answer

You've previewed enough free CISM questions. Unlock CISM for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Recovery Time Objective (RTO)#Business Continuity Planning#Disaster Recovery#BCP Metrics
Full CISM PracticeBrowse All CISM Questions