CISM · Question #493
Senior management wants to thoroughly test a disaster recovery plan (DRP) for a mission-critical system. Which of the following would provide the MOST reliable results?
The correct answer is A. Full interruption test. A full interruption test completely shuts down the primary system and forces a failover to the disaster recovery environment, exactly as would occur in a real disaster. Because it reflects actual conditions, it provides the most reliable and realistic assessment of the DRP's viab
Question
Senior management wants to thoroughly test a disaster recovery plan (DRP) for a mission-critical system. Which of the following would provide the MOST reliable results?
Options
- AFull interruption test
- BParallel test
- CSimulation test
- DStructured walk-through
How the community answered
(54 responses)- A72% (39)
- B7% (4)
- C17% (9)
- D4% (2)
Explanation
A full interruption test completely shuts down the primary system and forces a failover to the disaster recovery environment, exactly as would occur in a real disaster. Because it reflects actual conditions, it provides the most reliable and realistic assessment of the DRP's viability. A parallel test (B) runs both primary and DR systems simultaneously, reducing risk but potentially masking failover issues. A simulation test (C) exercises the plan through a scenario without actual failover. A structured walk-through (D) is a tabletop exercise where participants discuss steps without any system activity. Each step up from walk-through toward full interruption increases realism and reliability of results.
Topics
Community Discussion
No community discussion yet for this question.