Detailed business continuity plans (BCPs) should be PRIMARILY based on:

The correct answer is D. strategies validated by senior management. Detailed business continuity plans (BCPs) should be primarily based on strategies that are validated by senior management. This ensures that the BCP aligns with the organization's overall goals, risk appetite, and resource allocation, and that senior leadership is committed to…

Submitted by kev92· Apr 18, 2026Information Security Governance

Question

Detailed business continuity plans (BCPs) should be PRIMARILY based on:

Options

  • Acapabilities of available local vendors.
  • Bstrategies that cover all applications.
  • Ccost and resources needed to execute.
  • Dstrategies validated by senior management.

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    13% (3)
  • D
    78% (18)

Explanation

Detailed business continuity plans (BCPs) should be primarily based on strategies that are validated by senior management. This ensures that the BCP aligns with the organization's overall goals, risk appetite, and resource allocation, and that senior leadership is committed to supporting and executing the plan when needed.

Topics

#Business Continuity Planning#Governance#Strategic Direction#Senior Management Oversight