Senior management has requested a budget cut for the information security program in the coming fiscal year. Which of the following should be the information security manager's FIRST course of action?

The correct answer is A. Analyze the impact to the information security program. The first action an information security manager should take when facing a budget cut is to analyze the potential impact on the security program and the organization's risk posture.

Submitted by kim_seoul· Apr 18, 2026Information Security Program Development and Management

Question

Senior management has requested a budget cut for the information security program in the coming fiscal year. Which of the following should be the information security manager's FIRST course of action?

Options

  • AAnalyze the impact to the information security program.
  • BAdvise business unit heads of potential changes to the information security program.
  • CEvaluate cost savings within existing implementations.
  • DRe-prioritize information security implementation and operations.

How the community answered

(44 responses)
  • A
    82% (36)
  • B
    9% (4)
  • C
    7% (3)
  • D
    2% (1)

Why each option

The first action an information security manager should take when facing a budget cut is to analyze the potential impact on the security program and the organization's risk posture.

AAnalyze the impact to the information security program.Correct

Before any other action, the information security manager must understand the direct consequences of the budget cut on existing controls, planned initiatives, and the overall ability to manage risk. This analysis provides the necessary data to inform further decisions, communicate risks to stakeholders, and justify alternative approaches.

BAdvise business unit heads of potential changes to the information security program.

Advising business unit heads prematurely without a clear understanding of the impact could cause unnecessary alarm or provide inaccurate information.

CEvaluate cost savings within existing implementations.

While evaluating cost savings is a subsequent step, the initial and most critical action is to assess the potential damage or reduced capability due to the requested cut.

DRe-prioritize information security implementation and operations.

Reprioritization is a logical next step after understanding the full impact of the budget cut on current priorities and risk levels.

Concept tested: Information security budget management

Topics

#Budget management#Program management#Impact analysis#Strategic planning