nerdexam
Isaca

CISA · Question #469

Reviewing which of the following would provide the BEST indication that a project is progressing as planned?

The correct answer is B. Earned value analysis (EVA) results. Earned value analysis (EVA) integrates project scope, schedule, and cost to measure project performance objectively. It provides a clear indication of whether the project is on track regarding both progress and budget, making it the best indicator that a project is progressing as

Submitted by anna_se· Apr 18, 2026Information Systems Acquisition, Development, and Implementation

Question

Reviewing which of the following would provide the BEST indication that a project is progressing as planned?

Options

  • ATraceability matrix
  • BEarned value analysis (EVA) results
  • CIdentification of the critical path
  • DWork breakdown structure

How the community answered

(63 responses)
  • A
    13% (8)
  • B
    75% (47)
  • C
    8% (5)
  • D
    5% (3)

Explanation

Earned value analysis (EVA) integrates project scope, schedule, and cost to measure project performance objectively. It provides a clear indication of whether the project is on track regarding both progress and budget, making it the best indicator that a project is progressing as planned.

Topics

#Earned Value Analysis#Project Management#Project Progress Tracking