CISA · Question #469
Reviewing which of the following would provide the BEST indication that a project is progressing as planned?
The correct answer is B. Earned value analysis (EVA) results. Earned value analysis (EVA) integrates project scope, schedule, and cost to measure project performance objectively. It provides a clear indication of whether the project is on track regarding both progress and budget, making it the best indicator that a project is progressing as
Question
Reviewing which of the following would provide the BEST indication that a project is progressing as planned?
Options
- ATraceability matrix
- BEarned value analysis (EVA) results
- CIdentification of the critical path
- DWork breakdown structure
How the community answered
(63 responses)- A13% (8)
- B75% (47)
- C8% (5)
- D5% (3)
Explanation
Earned value analysis (EVA) integrates project scope, schedule, and cost to measure project performance objectively. It provides a clear indication of whether the project is on track regarding both progress and budget, making it the best indicator that a project is progressing as planned.