Scope creep in a project can BEST be controlled by:

The correct answer is C. assessing the impact of requested changes. The best way to control scope creep in a project is by assessing the impact of requested changes. Scope creep often occurs when changes or additions to the project are made without properly evaluating their impact on the project’s scope, resources, timeline, and costs. By assessi

Submitted by lars.no· Apr 18, 2026Information Systems Acquisition, Development and Implementation

Question

Scope creep in a project can BEST be controlled by:

Options

  • Aperforming user acceptance tests
  • Bmanaging project costs
  • Cassessing the impact of requested changes
  • Dbalancing IT resource allocation

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    8% (2)
  • C
    85% (22)
  • D
    4% (1)

Explanation

The best way to control scope creep in a project is by assessing the impact of requested changes. Scope creep often occurs when changes or additions to the project are made without properly evaluating their impact on the project’s scope, resources, timeline, and costs. By assessing the impact of each requested change, the project team can ensure that changes are aligned with project objectives and that any adjustments are properly managed, preventing uncontrolled expansion of the project scope.

Topics

#Scope creep#Project management#Change control#Impact assessment