CISA · Question #421
An organization has been struggling with unsuccessful change rollbacks due to unreliable images. Which of the following would be an IS auditor's BEST recommendation in this situation?
The correct answer is B. Implement an approved baseline build. Unreliable images used for rollbacks indicate the absence of a controlled, verified baseline. Implementing an approved baseline build establishes a known-good, tested, and authorized system configuration that can be reliably restored during a rollback. This directly addresses…
Question
An organization has been struggling with unsuccessful change rollbacks due to unreliable images. Which of the following would be an IS auditor’s BEST recommendation in this situation?
Options
- AImplement additional approvals for future releases
- BImplement an approved baseline build
- CImplement an approved continuous integration model
- DImplement tiered incident response procedures
How the community answered
(50 responses)- A8% (4)
- B78% (39)
- C10% (5)
- D4% (2)
Explanation
Unreliable images used for rollbacks indicate the absence of a controlled, verified baseline. Implementing an approved baseline build establishes a known-good, tested, and authorized system configuration that can be reliably restored during a rollback. This directly addresses the root cause of the problem. Additional approvals (A) add governance overhead but do not fix image reliability. A continuous integration model (C) improves development pipelines but does not inherently solve rollback image reliability. Tiered incident response (D) improves how incidents are managed but does not resolve the underlying cause of failed rollbacks.