CISA · Question #396
A local insurance company has decided to migrate an in-house accounting solution to a purchased enterprise resource planning (ERP) solution. The project is entering the user acceptance testing (UAT)…
The correct answer is A. UAT has started before functional testing is complete. The greatest risk to the effectiveness of the User Acceptance Testing (UAT) phase is starting UAT before functional testing is complete. Functional testing ensures that the system behaves as expected from a technical perspective. If UAT begins prematurely, there is a risk that…
Question
A local insurance company has decided to migrate an in-house accounting solution to a purchased enterprise resource planning (ERP) solution. The project is entering the user acceptance testing (UAT) phase. Which of the following would pose the GREATEST risk to the effectiveness of the UAT?
Options
- AUAT has started before functional testing is complete
- BUAT environment is an exact copy of production data
- CUAT includes business users who were not involved with the project
- DUAT is conducted by senior management
How the community answered
(51 responses)- A75% (38)
- B4% (2)
- C8% (4)
- D14% (7)
Explanation
The greatest risk to the effectiveness of the User Acceptance Testing (UAT) phase is starting UAT before functional testing is complete. Functional testing ensures that the system behaves as expected from a technical perspective. If UAT begins prematurely, there is a risk that the system may have unresolved technical issues, which could lead to incorrect testing results or missed defects, ultimately undermining the effectiveness of UAT and delaying the project.
Topics
Community Discussion
No community discussion yet for this question.