CISA · Question #383
After the successful release of an application system, business stakeholders are planning to organize a post-implementation review to determine whether the system satisfies business needs. Which of th
The correct answer is B. Business use cases. The most important aspect to review during the planning sessions for a post-implementation review is the business use cases. These use cases outline the specific business requirements and objectives the application was meant to address. Reviewing them ensures that the system's fu
Question
After the successful release of an application system, business stakeholders are planning to organize a post-implementation review to determine whether the system satisfies business needs. Which of the following is MOST important to review during the planning sessions?
Options
- ABusiness impact analysis (BIA)
- BBusiness use cases
- CApplication defect tracker
- DManagement dashboard information
How the community answered
(32 responses)- A9% (3)
- B72% (23)
- C3% (1)
- D16% (5)
Explanation
The most important aspect to review during the planning sessions for a post-implementation review is the business use cases. These use cases outline the specific business requirements and objectives the application was meant to address. Reviewing them ensures that the system's functionality aligns with the original business needs, helping to determine whether the system delivers the expected value and meets stakeholders' expectations.