Vulnerability identification should begin in which phase of an in-house software development project?

The correct answer is B. Design phase. Vulnerability identification should begin in the design phase of an in-house software development project. Identifying and addressing security concerns early in the design phase helps mitigate risks before the development and implementation phases, reducing the chances of…

Submitted by suresh_in· Apr 18, 2026Information Systems Acquisition, Development, and Implementation

Question

Vulnerability identification should begin in which phase of an in-house software development project?

Options

  • ADevelopment phase
  • BDesign phase
  • CRequirements definition phase
  • DImplementation phase

How the community answered

(29 responses)
  • A
    7% (2)
  • B
    86% (25)
  • C
    3% (1)
  • D
    3% (1)

Explanation

Vulnerability identification should begin in the design phase of an in-house software development project. Identifying and addressing security concerns early in the design phase helps mitigate risks before the development and implementation phases, reducing the chances of vulnerabilities being introduced later in the process.

Topics