An IS auditor is reviewing an origination's release management practices and observes inconsistent and inaccurate estimation of the size and complexity of business application development projects…
The correct answer is D. Function point analysis. An IS auditor should recommend Function Point Analysis to address inconsistent and inaccurate estimations of software project size and complexity.
Question
An IS auditor is reviewing an origination’s release management practices and observes inconsistent and inaccurate estimation of the size and complexity of business application development projects. Which of the following should the auditor recommend to address this issue?
Options
- AAgile development approach
- BCritical path methodology
- CRapid application development
- DFunction point analysis
How the community answered
(42 responses)- A10% (4)
- B14% (6)
- C5% (2)
- D71% (30)
Why each option
An IS auditor should recommend Function Point Analysis to address inconsistent and inaccurate estimations of software project size and complexity.
Agile development approach is a methodology for managing software projects, not specifically a technique for estimating project size or complexity in a consistent, quantifiable manner.
Critical Path Methodology (CPM) is used for scheduling and identifying the longest sequence of tasks, but it doesn't primarily address the initial estimation of the size or complexity of the project itself.
Rapid Application Development (RAD) is a software development methodology emphasizing rapid prototyping and iterative development, not a method for precisely estimating project size and complexity upfront.
Function Point Analysis (FPA) is a standardized method for objectively measuring the functional size of a software system based on user-visible functionality, independent of the technology used. By quantifying project size in a consistent manner, FPA helps improve the accuracy and consistency of effort and cost estimations for software development projects.
Concept tested: Software project estimation, Function Point Analysis