Question
Which of the following is an IS auditor's BEST course of action when the auditee indicates that a corrective action plan for a high-risk finding will take longer than expected?
Options
- ADetermine if an interim compensating control has been implemented.
- BRequire that remediation is completed in the agreed timeframe.
- CAccept the longer target date and document it in the audit system.
- DEscalate the overdue finding to the audit committee.
Unlock CISA to see the answer