Which of the following is the MOST cost-effective way to determine the effectiveness if a business continuity plan (BCP)?
The correct answer is D. Tabletop exercise. A tabletop exercise involves gathering key stakeholders to discuss and simulate a scenario in which the BCP would be activated. This method is generally less resource-intensive and costly compared to full operational tests or stress tests, which require significant planning and r
Question
Which of the following is the MOST cost-effective way to determine the effectiveness if a business continuity plan (BCP)?
Options
- APost-implementation review
- BFull operational test
- CStress test
- DTabletop exercise
How the community answered
(22 responses)- A14% (3)
- B9% (2)
- C5% (1)
- D73% (16)
Explanation
A tabletop exercise involves gathering key stakeholders to discuss and simulate a scenario in which the BCP would be activated. This method is generally less resource-intensive and costly compared to full operational tests or stress tests, which require significant planning and resources to execute. Tabletop exercises provide valuable insights into the plan's effectiveness, identify gaps, and facilitate discussions on improvements without the need for full operational disruption. While post-implementation reviews can be beneficial, they typically occur after a plan has been executed rather than testing it in a simulated scenario. Therefore, a tabletop exercise is the most cost-effective option for evaluating the effectiveness of a BCP.