CISA · Question #151
An IS auditor evaluating the change management process must select a sample from the change log. What is the BEST way for the auditor to confirm the change log is complete?
The correct answer is B. Take the last change from the system and trace it back to the log.. To confirm completeness of a change log, the auditor must work from the authoritative source (the system itself) back to the log - not the other way around. Taking a change from the system and tracing it to the log tests whether all system changes were recorded. If you start from
Question
An IS auditor evaluating the change management process must select a sample from the change log. What is the BEST way for the auditor to confirm the change log is complete?
Options
- AObtain management attestation of completeness.
- BTake the last change from the system and trace it back to the log.
- CTake an item from the log and trace it back to the system.
- DInterview change management personnel about completeness.
How the community answered
(37 responses)- A8% (3)
- B73% (27)
- C16% (6)
- D3% (1)
Explanation
To confirm completeness of a change log, the auditor must work from the authoritative source (the system itself) back to the log - not the other way around. Taking a change from the system and tracing it to the log tests whether all system changes were recorded. If you start from the log and trace to the system (C), you are testing validity/accuracy, not completeness - items in the log did happen, but items that happened may not be in the log. Management attestation (A) and interviews (D) are not objective evidence and provide low assurance over completeness.