CISA · Question #118

A bank performed minor changes to the interest calculation computer program. Which of the following techniques would provide the STRONGEST evidence to determine whether the interest calculations are…

The correct answer is D. Parallel simulation using audit software. For verifying minor changes to an interest calculation program, parallel simulation using audit software provides the strongest evidence by independently re-calculating results and comparing them against the system's output.

Submitted by yuki_2020· Apr 18, 2026Information Systems Acquisition, Development, and Implementation

Question

A bank performed minor changes to the interest calculation computer program. Which of the following techniques would provide the STRONGEST evidence to determine whether the interest calculations are correct?

Options

  • AReview of the quality assurance (QA) test results
  • BManual verification of a sample of the results
  • CSource code review
  • DParallel simulation using audit software

How the community answered

(13 responses)
  • A
    23% (3)
  • B
    8% (1)
  • C
    15% (2)
  • D
    54% (7)

Why each option

For verifying minor changes to an interest calculation program, parallel simulation using audit software provides the strongest evidence by independently re-calculating results and comparing them against the system's output.

AReview of the quality assurance (QA) test results

Review of QA test results only provides evidence of what the development team tested and found, not an independent verification of the actual production calculations.

BManual verification of a sample of the results

Manual verification of a sample of results is time-consuming and prone to human error, and a small sample may not cover all scenarios, making it less robust than a full parallel simulation.

CSource code review

Source code review can identify potential logic errors but does not confirm that the compiled program is actually running correctly with real data in the production environment.

DParallel simulation using audit softwareCorrect

Parallel simulation using audit software involves processing actual data through a known good program (the audit software's calculation logic) and comparing the results directly with the output generated by the bank's modified interest calculation program. This provides independent and strong evidence of the correctness of the calculations because it tests the production system's actual processing against an objective standard.

Concept tested: Audit techniques for program change verification

Source: https://www.isaca.org/resources/isaca-journal/issues/2012/volume-6/auditing-systems-with-computer-assisted-audit-techniques

Topics

#Audit Techniques#Application Testing#Data Integrity#Parallel Simulation

Community Discussion

No community discussion yet for this question.