Which of the following statements about the change severity assessment 'environment' impact are true? 1. The amount of other activity happening at the same time as the charge is a factor 2. The…

The correct answer is C. Both 1 and Z are true. The change severity assessment is a tool to evaluate the impact of a change on different dimensions, such as environment, organization, individuals, and project. The environment dimension considers the external and internal factors that affect the change, such as market…

Change Impact Assessment

Question

Which of the following statements about the change severity assessment 'environment' impact are true? 1. The amount of other activity happening at the same time as the charge is a factor 2. The common values and behaviors in the organization is a factor.

Options

  • AOnly1 is true
  • BOnly 2 is true
  • CBoth 1 and Z are true
  • DNeither 1 or 2 is true

How the community answered

(58 responses)
  • A
    5% (3)
  • B
    3% (2)
  • C
    90% (52)
  • D
    2% (1)

Explanation

The change severity assessment is a tool to evaluate the impact of a change on different dimensions, such as environment, organization, individuals, and project. The environment dimension considers the external and internal factors that affect the change, such as market conditions, competitors, regulations, culture, values, and behaviors. The amount of other activity happening at the same time as the change and the common values and behaviors in the organization are both factors that belong to the environment dimension.

Topics