CGRC · Question #506
The Software Development Life-Cycle phase that maps to RMF Step 2 (select controls), Task 4, SP Approval? Response:
The correct answer is A. Development/Acquisition. RMF Step 2 (Select Controls) and its associated task for security plan approval typically aligns with the Development/Acquisition phase of the Software Development Life-Cycle.
Question
The Software Development Life-Cycle phase that maps to RMF Step 2 (select controls), Task 4, SP Approval? Response:
Options
- ADevelopment/Acquisition
- BOperation/Maintenance
- CMission/business process
- DCriticality/Sensitivity
How the community answered
(39 responses)- A87% (34)
- B3% (1)
- C8% (3)
- D3% (1)
Why each option
RMF Step 2 (Select Controls) and its associated task for security plan approval typically aligns with the Development/Acquisition phase of the Software Development Life-Cycle.
During the Development/Acquisition phase, security requirements are defined, controls are selected, and the security plan is developed and approved to ensure security is integrated into the system design or procurement. This aligns directly with RMF Step 2, where controls are chosen and approved for implementation.
The Operation/Maintenance phase occurs after controls have been selected and implemented, focusing on their ongoing monitoring and effectiveness.
Mission/business process describes the overarching purpose, not a specific SDLC phase.
Criticality/Sensitivity refers to the impact level of information, which informs control selection but is not an SDLC phase itself.
Concept tested: RMF to SDLC Mapping - Control Selection
Source: https://csrc.nist.gov/publications/detail/sp/800-37/rev-2/final