CGRC · Question #258
Management wants you to create a visual diagram of what resources will be utilized in the project deliverables. What type of a chart is management asking you to create? Response:
The correct answer is B. Resource breakdown structure. A Resource Breakdown Structure (RBS) is a hierarchical chart that visually organizes the types of resources required for project deliverables.
Question
Management wants you to create a visual diagram of what resources will be utilized in the project deliverables. What type of a chart is management asking you to create? Response:
Options
- AWork breakdown structure
- BResource breakdown structure
- CRACI chart
- DRoles and responsibility matrix
How the community answered
(27 responses)- A4% (1)
- B89% (24)
- D7% (2)
Why each option
A Resource Breakdown Structure (RBS) is a hierarchical chart that visually organizes the types of resources required for project deliverables.
A Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team, not specifically resources.
A Resource Breakdown Structure (RBS) is a hierarchical decomposition of resources by category and type used in project management. It provides a visual diagram of all resources-human, equipment, materials, and supplies-needed for project deliverables, aligning with management's request.
A RACI chart (Responsible, Accountable, Consulted, Informed) defines roles and responsibilities for specific tasks or deliverables, not a general breakdown of all utilized resources.
A roles and responsibility matrix, like a RACI chart, maps specific responsibilities to individuals or roles, rather than detailing the types of resources utilized.
Concept tested: Project management structures - Resource Breakdown Structure